Ground up Construction. Contract Value $5.4MM Mechanical and $2MM Plumbing consisting of;

  • HVAC
    • Multistack Air Cooled Chiller
    • Marley Closed-Circuit Fluid Cooler
    • (161) AAON Water Source Heat Pumps
    • BAS Controls
    • BIM Coordination with Pinnacle
    • 75,000 lbs of sheet metal ductwork
    • 14,500 L.F. of hydronic piping
    • 3,200ft of welds
    • 30,100 man hours
  • Plumbing
    • Domestic water, DWV, Gas Piping, Compressed Air, Wash Rack, Fixtures
    • Converted Government from cast iron to PVC due to corrosive nature of environment
    • 6,800 man hours
    • 18,900 L.F. of piping